Construction Description - Sept. 8 - 17
Work on the storm system will continue with installation of soil cells, dry wells and storm mains in Zone 1 , 2, 3 and 4. Excavation and the installation of soil cells will limit the access to certain businesses in Zone 1 & 2 (from Caribou intersection and north to Willock & Sax Gallery/Old Crag Cabin).
Surveying is identifying the precise extent of the required excavations. Every effort will be made to minimize the impact of closures and alternate access routes will be established when possible.
Removal of the water line injection points in Zone 3 is occurring next week. Injection points remain until lines are chlorinated and tested. The removal requires a closure of the sidewalk and excavation in front of these buildings again. Dates for these closures are scheduled as:
- Tuesday, September 8 – Townhouse Building / Perfect Image & Bear Street Mall
- Wednesday, September 9 – CMH, BPL Staff Accom, Saltlik & Home Hardware
- Thursday, September 10 – 225 Bear Street
- Friday, September 11 – 204 Wolf Street & Cascade Plaza West (Circle K)
Bear Street access to businesses during these closures will not be available on those respective days.
Pressure testing and chlorination of the water system in Zone 4 (Wolf Street intersection) will continue throughout the week.