Annual Road Repaving
Road OverlayEach spring, the Town of Banff repaves several streets, removing the top layer of asphalt and then repaving roads to create a smooth driving surface.

The following roads will receive new asphalt in 2019:
  • Banff Ave from Elk Street to Badger Street
  • Rabbit Street from Banff Ave to Marten Street
  • Park Ave
  • The entrance section of Nahanni Drive closest to Mountain Ave
  • 400 block of Muskrat Street 
  • Marmot Street
  • Deer Lane between Antelope and Fox Streets

All work is weather dependent, so times and dates cannot be confirmed.

During the repaving process:
  • Crews will remove barricades when it is safe to use the street again
  • Expect minor delays 
  • Please do not approach work sites or attempt to cross newly paved streets. New pavement is extremely hot and heavy machines are difficult to stop 
  • No Parking signs will be put up prior to the work beginning

Contact
Engineering Department
403.762.1210